Himachal: River diversion completed in Shongtong project

Himachal Pradesh: Himachal Pradesh Power Corporation Limited (HPPCL) officials informed a cabinet sub-committee on Wednesday that the river diversion work at the Shongtong Hydropower Project has been completed and other works, including the construction of a barrage, will be completed soon. At the cabinet sub-committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi, officials gave a detailed presentation on the progress of the 450 MW project.

They stated that 81.91 percent of the feeder tunnel construction has been completed, and hydro-mechanical works have begun. HPPCL Managing Director Abid Hussain Sadiq said the corporation aims to commission one unit of the project by December 2026. He added that key milestones, such as widening three vertical pressure shafts and completing Unit 1 of the powerhouse, have been achieved. Expressing satisfaction with the progress, Negi directed officials to expedite work on the Lippa Hydropower Project as well.

हिंदी की ताजा खबरें पढने के लिए यहाँ क्लिक करें|

Related Articles

Back to top button
हिंदी की ताजा खबर पढने के लिए यहाँ क्लिक करें|
Bhumi Pednekar’s desi avatar seen Rakul Preet Singh’s bold avatar set the internet on fire Latest Photoshoot of Rachel David Check out the latest photos of Shriya Saran for Hello Mag India awards Rakul Preet Singh Sizzles in Purple Saree Sizzling Photoshoot of Raai Laxmi Glamorous Stills of Huma Qureshi Nora Fatehi Flaunts her Sexy Figure in Transparent Gown Vacation Photos of Chetna Pande Enjoying in her own Style Latest Photoshoot of Samyuktha Menon in White Saree