Mumbai News: Central Railway completes platform widening work in Thane after 63 hours of mega block

Mumbai: The Central Railway (CR) on Sunday said it has completed the widening work of platforms 5 and 6 at Thane. CR shared details about the special block for infrastructure upgradation work at the Thane station. It said platforms 5/6 have been widened by 2-3 metres over a length of 587 metres.

63-hour mega block: Central Railway says travel only if necessary; BEST to run additional bus services The Central Railway had initiated a 63-hour mega block at Thane railway station and a 36-hour special block at Chhatrapati Shivaji Maharaj Terminus.

The mega block began from midnight of May 30-31 (Thursday-Friday night). A CR official said the platform widening project involved the use of 750 pre-cast hollow blocks and required the coordination of 400 workers, 20 teams and 10 contractors. The official said 935 trains were cancelled during the 63-hour period.

हिंदी की ताजा खबरें पढने के लिए यहाँ क्लिक करें|

Related Articles

Back to top button
हिंदी की ताजा खबर पढने के लिए यहाँ क्लिक करें|
Bhumi Pednekar’s desi avatar seen Rakul Preet Singh’s bold avatar set the internet on fire Latest Photoshoot of Rachel David Check out the latest photos of Shriya Saran for Hello Mag India awards Rakul Preet Singh Sizzles in Purple Saree Sizzling Photoshoot of Raai Laxmi Glamorous Stills of Huma Qureshi Nora Fatehi Flaunts her Sexy Figure in Transparent Gown Vacation Photos of Chetna Pande Enjoying in her own Style Latest Photoshoot of Samyuktha Menon in White Saree